LONG LAKE PIER UPGRADE
LOCATION: LONG LAKE, NY

.jpg)
Construction completed by Kubricky Construction Corporation
Budget: $227,320
Construction started Late in October 2017 and was shut down due to rising lake levels on November 10, 2018.
Construction resumed June 18, 2018 and was completed June 29, 2018 for use over the July 4th holiday.