Warrensburg Watermain Bridge Crossing
The Town of Warrensburg acted quickly to replace a failing antiquated 8” steel water main bridge crossing that was deteriorating and leaking within the NYS Department of Transportation right-of-way. The Town purchased materials and installed 5” temporary bypass hose to allow for design, permitting and bidding to be completed. Reale Construction, Inc. was awarded the project and construction was completed ahead of schedule for the project.
Project Cost: $182,470
Contractor(s): Reale Construction, Inc.
Funding Agencies: Municipal Funds
Project Status: Completed in 2022