top of page

Stamford Water System Upgrade

The project consisted of two independent but critical construction projects: (1) the replacement of a 1.5 million-gallon concrete storage tank with a new 750,000-gallon glass-fused to steel storage tank and (2) the replacement of approximately 11,500 feet of water main replacement and approximately 3,600 feet of distribution system connector piping (i.e. looping) to address water quality issues. The water main construction included approximately 11,500 feet of water main replacement, and approximately 3,600 feet of distribution system connector piping (i.e. looping) to address water quality issues. The storage tank project involved replacing the existing 1.5 million-gallon storage tank (which was in a state of disrepair and is planned to be demolished) with a new 750,000-gallon tank in the area adjacent to the current tank (at the end of Kirkner Hill Road). Cedarwood worked with USDA Rural Development, NYS Environmental Facilities Corporation, and NYS Homes & Community Renewal funding agencies to complete the project. Phase I has been completed, with Phase II scheduled to be completed in 2023.


Project Cost: $6.2 million

Contractor(s): Phase I: Tweedie Construction Services, Inc.

Statewide Aquastore, Inc.

Vacri Constuction Corporation

Phase II: Bellamy Construction Company, Inc.

Funding Agencies: NYS EFC, NYS OCR, & USDA RD

Project Status: Completion scheduled for 2023

Project Gallery

bottom of page